This page broadly describes our planned approach for the project to bring the City of Adelaide clipper ship back to South Australia. It is anticipated that these details will be further refined during detailed design and planning. They are dependent on a detailed site survey as well as the equipment and methods ultimately used.

The plans are presented using a Work Breakdown Structure, which is a fundamental project management technique for defining and organising the total scope of a project, using a hierarchical tree structure.

The project is broken down into a series of Phases.    Each phase is then broken down into a series of Stages.

The high level phases are:

  • Phase 1: Remove the clipper from the slipway.
  • Phase 2: Transport the clipper to South Australia.
  • Phase 3: Preparations to receive the clipper in South Australia.



Irvine Harbour
Irvine Harbour

Present Slipway Arrangement
Present Slipway Arrangement



Phase 1 - Remove the Clipper from the Slipway

The objective of this phase is to remove the clipper from the slipway and move her onto a barge.    The stages within this Phase are:

1.1    Technical Preparations - development of detailed plans and drawings for subsequent stages of project.

1.2    Cradle - construct the transportation cradle for subsequent lifting and transporting of clipper.

Cradle
Construct Cradle



1.3    Clipper - prepare the clipper for moving.

  •  
    • Install transportation cradle.
    • Prepare clipper for moving – Shore and brace parts of ship in accordance with Naval Architects report.
    • Raise and level the ‘City of Adelaide’ using hydraulic jacks.
    • Support the transport cradle on temporary concrete blocks.
    • Remove the existing cradle.
Raise Clipper
Raise Clipper



1.4    Slipway - remove bund and dredge in way of slipway.

  •  
    • Fill and compact the slipway with gravel/crushed rock/dirt to Engineer’s specification.
    • Level the bund at the end of the slipway and compact.
Prepare Road Base
Prepare Road Base



1.5    Barge - land on sill and ballast down barge.

  •  
    • Bring in flat-deck barge, ballast down and secure.
    • Fill and compact the gap between the barge and existing bund at end of slipway.
    • Hoist clipper with multi-wheel transporters.
Bring in Barge
Bring in Barge



1.6    Transfer - push transporters and clipper with prime movers on to barge.

Transfer Clipper
Transfer Clipper



1.7    Towage - deballast barge and tow barge and clipper to an Irvine wharf, pontoon or other interim location while awaiting dockship/heavy-lift ship.

Depart Site
Depart Site

Transit River Irvine
Transit River Irvine





 

Please Donate

Help save the 'City of Adelaide'

Please donate to help save this historic ship, or if this site was helpful in your genealogy research. Every dollar, pound, euro and other denomination helps.

Petition Tally

Petition Signatures
Federal1866
State1225
Click here to sign 

Member Login

Who's Online

We have 82 guests online
None
Share this page on facebook

Statistics

Members : 243
Content : 517
Web Links : 123
Content View Hits : 859927

Newsflash

NEW! - We now have over 1,000 crew records on-line.

On 6th August 1864 the brand-new City of Adelaide left the Thames docklands of central London to sail for South Australia with her passengers, 100 tons of coal, 11,300 items of general cargo (bales, cases, casks, packages and bundles) - and a crew of 38 men ... Read more >>